Permit Levels for 45CSR13

 

Minor Source Construction, Modification, Relocation, Temporary, General and Administrative Update Permits, and Permission to Commence Construction
(Revised June 2009)

Click here for a printer-friendly version in Adobe Acrobat.

 

 

 

 

 Public Notice

Review Period as per Rule 

Application Fee 

Criteria 

Application Type 

Permit Determination  None  30 working days  None  No permit required if less than modification AND change does not result in an increase above a numerical limit in permit  Written Request OR Permit Determination Form
Administrative Update
(Class I)
 None  60 days  None  Decrease in emissions OR permanent removal of equipment OR more stringent requirements OR change in MRR that is equivalent or superior  Written Request OR Permit Determination Form OR Application for Permit
Administrative Update
(Class II)
 30 days (applicant)  60 days  $300 + 45CSR22 fees  Less than modification  Permit Determination Form OR Application for Permit
Construction Permit  30 days (applicant) + 30 days DAQ *  90 days  $1,000 + 45CSR22 fees  6pph AND 10tpy of any regulated air pollutant OR 144ppd of any regulated air pollutant OR 2pph OR 5tpy of aggregated HAP OR 45CSR27 TAP (10% increase if above BAT triggers or increase to BAT triggers) OR subject to applicable standard or rule  Application for Permit
Modification Permit 30 days (applicant) + 30 days DAQ *   90 days $1,000 + 45CSR22 fees   Same as construction Application for Permit 
Relocation Permit  30 days (applicant)  45 days  $1,000 + 45CSR22 fees  No emissions increase or change in facility design or equipment  Application for Permit
Temporary Permit  30 days (applicant)  45 days  $1,000 + 45CSR22 fees  Same as construction, but for limited period of time (6 months initially, but can be extended up to 12 additional months by written request)  Application for Permit
General Permit (Class I)  None  45 days  $250  Same as construction, but subject to specific eligibility requirements  Registration Application
General Permit (Class II)  30 days (applicant) 45 days   $500 + 45CSR22 fees Same as construction, but subject to specific eligibility requirements   Registration Application

 

*Additional provisions may apply (such as requiring a commercial display advertisement and/or posting of sign).