Permit Levels for 45CSR13

Overview

Minor Source Construction, Modification, Relocation, Temporary, General and Administrative Update Permits, and Permission to Commence Construction (Revised June 2009)

Resources


Public Notice Review Period as per Rule Application Fee Criteria Application Type
Permit Determination None 30 working days None No permit required if less than modification AND change does not result in an increase above a numerical limit in permit Written Request OR Permit Determination Form
Administrative Update (Class I) None 60 days None Decrease in emissions OR permanent removal of equipment OR more stringent requirements OR change in MRR that is equivalent or superior Written Request OR Permit Determination Form OR Application for Permit
Administrative Update (Class II) 30 days (application 60 days $300 + 45CSR22 fees Less than modification Permit Determination Form OR Application for Permit
Construction Permit 30 days (application) + 30 days DAQ* 90 days $1,000 + 45CSR22 fees 6pph AND 10tpy of any regulated air pollutant OR 144ppd of any regulated air pollutant OR 2pph OR 5tpy of aggregated HAP OR 45CSR27 TAP (10% increase if above BAT triggers an increase to BAT triggers) OR subject to applicable standard or rule Application for Permit
Modification Permit 30 days (applicant) + 30 days DAQ* 90 days $1,000 + 45CSR22 fees Same as construction Application for Permit
Relocation Permit 30 days (applicant) 45 days $1,000 + 45CSR22 fees No emissions increase or change in facility design or equipment Application for Permit
Temporary Permit 30 days (applicant) 45 days $1,000 + 45CSR22 fees Same as construction, but for limited period of time (6 months initially, but can be extended up to 12 additional months by written request) Application for Permit
General Permit (Class I) None 45 days $250 Same as construction, but subject to specific eligibility requirements Registration Application
General Permit (Class II) 30 days (applicant) 45 days $500 + 45CSR22 fees Same as construction, but subject to specific eligibility requirements Registration Application

* Additional provisions may apply (such as requiring a commercial display advertisement and/or posting of sign.​